Projects / Frampton on Severn Community Centre Heating Improvement Project

Frampton on Severn Community Centre Heating Improvement Project

This project is the first of a three stage programme to bring the Community Centre up to modern standards. Following advice from the Severn Wye Energy Agency and other advisers, we will first improve the insulation of the main hall which was built in 1936 and is inadequately insulated and heated. We will provide:
(i) Cavity wall and internal insulation
(ii) Double glazing to windows
(iii) Insulation for roof space over the stage, currently open to the roof
(iv) Insulation of suspended ceiling
(v) Insulated fire doors to exit
(vi) Re-pointing to external (north) wall
(vii) Replace obsolete/defective windows and doors to south of building.

EB Number

872910

Estimated Start

01/07/2012

Estimated Finish

01/09/2012

Postcode

GL2 7HG

Amount

20000.00

Object Type(s)

D

Find a Funder for Your Project.