Projects / Remedial works:erosion limitation:Mouth of Burn o’ Fochabers

Remedial works:erosion limitation:Mouth of Burn o’ Fochabers

Rock armour to be placed on the south side of burn along boundary wall of adjacent premises to give protection against future spates. Deposited material on the north side from previous high flows to be excavated allowing subsequent high flows to flow easier into the Spey, thereby reducing pressure on the south side of the Burn. Excavated reducing pressure on the south side of the Burn. Excavated material to be placed on the south side to shore up the rock armour wall. Weaving willow walls to be constructed together with substantial planting of willow stems to further protect the area.

EB Number

372363

Estimated Start

01/04/2014

Estimated Finish

01/08/2014

Postcode

IV32 7PF

Amount

16615.80

Object Type(s)

D