Projects / Sunny Bank Vale – Maintenance 2

Sunny Bank Vale – Maintenance 2

Maintenance of Sunny Bank Vale to ensure the recently upgraded footpaths are kept in
good condition to allow the best use of the site by the general public.
Works include:
– Mow path verges once a month from April – October 2016
– Scrub control adjacent to footpaths
– Weed spray footpaths (April and September 2016)
– 2 days between April and October 2016 for other works (e.g. woodland maintenance, preparation of site for wild flower sowing, weed spraying)
This follows on from project 341010.555.

EB Number

341010

Estimated Start

01/02/2016

Estimated Finish

01/06/2017

Postcode

M43 6JZ

Amount

5664.00

Object Type(s)

D

Find a Funder for Your Project.