Topped Mountain Path

To repair and improve an existing pathway to the summit of Topped Mountain, including drainage, surfacing, trimming back of trees and shrubs, erection of kissing gates and repair of benches. The pathway was originally created in the early 1980’s. Since then, flooding as well as the passage of people and animals has taken its toll. At the moment the path is extremely rough and uneven, with a high risk of injury. The works also include repair to the car park/picnic area at the beginning of the walk.

EB Number

710382

Estimated Start

01/04/2006

Estimated Finish

01/07/2006

Postcode

BT30 9EF

Amount

13829.67

Object Type(s)

D